PPP - FC05
Question:
What architectural services listed below are NOT considered 'basic'.
- Construction administration services occuring more then 60 days after the date of subsantial completion, or the date anticipated in agreement.
- Document revisions due to enhancement of new laws, regulations after submissions.
- Responces to RFIs when the information requested is in the constract documents.
- Making inspections that exceed a negotiated number of inspectiond to determine if final completion is reached.
- Revisions to architectural documents caused by changes in the initial information, previouse instructions, or prior approvals from the owner.
- Revisions due to non-timely decisions by the owner.
- Commissioning
- LEED Certification
- Furniture, Furnishings, and Equipment Design
A. All of the Above
B. 1, 4, 5
C. None of the Above
D. 1, 2, 3, 4, 5, 6, 8